Initial risk level calculation
Similar questions: How to determine initial risk level? Where to select risk factors during
risk evaluation?
Risk factors names and description may vary from
one organization to another as well as the formula for initial risk calculation
may be different, depending on company’s policy. These parameters are being set
in General Settings by users with Administrator role.
- Go to module from
the home page or using the metro button menu. This opens the list of
existing risks.
- Select the risk you’re planning to calculate
initial risk for and click on its ID to open (for example ). From there in the left side menu go to Evaluation – Initial
risk level tab
- Select parameters of the risk matrix—risk
factors. They may be named differently in different tenants, but generally in
the industry such notions are used as Damage avoidance, Exposure, Probability
and Severity to locate a risk within the Risk Matrix.
- Selecting risk factors is normally a
team effort, since it takes judgement of several evaluation team members to choose
the correct value in the drop down list (values are explained in the list to
help make the correct selection)
- After all Risk factors are
entered, a formula will calculate the Initial risk index according to
the Risk Matrix and it will appear in the upper left of the screen
For
Initial risk level calculation Risk Factors should be selected without
considering mitigation measures that will be taken as a result of the Risk
Analysis. An initial level of Risk factors is being considered before
additional mitigation measures.
Related Articles
Residual risk level calculation
Similar questions: How to determine initial risk level? Where to select residual risk factors after mitigation measures? Risk factors names and description may vary from one organization to another as well as the formula for initial risk calculation ...
How to create a risk factor for initial risk calculation or edit the existing one?
Similar questions: Where to change risk factors used for Initial risk matrix? In order to change or add a risk factor user needs relevant rights within his/her Role in the tenant of CONFORMiT software. Refer to your administrator when necessary to ...
Creating and indicating risk consequences
Similar questions: Where to mention potential risk consequences? How to create or change consequences? Go to module from the home page or using the metro button menu. This opens the list of existing risks. Select the risk you’re wishing to indicate ...
Configuring the Risk Analysis (RA) module
Before configuring the ADR module, it is preferable to perform the steps listed in the article Initial Setup. The platform contains all the essential elements for an organization to perform ADRs according to industry best practices. However, it is ...
Filtering the Risk list
Similar questions: How to filter a risk list by certain residual risk? How to obtain the list of risks by selected unit(s)? How to view a list of Risk Analyses with the same tag (on the same stage)? User will be able to filter the list of Risk ...