Setting up the Risk Matrix

Setting up the Risk Matrix

How to set up the risk matrix field?

Similar questions:  Where to arrange the risk matrix?

In order to change or set up the risk matrix user needs relevant rights within his/her Role in the tenant of CONFORMiT software. Refer to your administrator when necessary to obtain the right to modify risk analysis components.

·         Go to  and in the Settings menu within Risk analysis select Risk matrix to open the tab with existing matrix field layout.

Matrix itself is an area in between horizontal and vertical axis (usually representing Severity of possible risk consequences and Probability or Likelihood of its occurrence) with separate smaller rectangular fields representing the risk estimation labelled with letters or numbers within the section that sets up axis parameters.

 

 

  1.  Value for each risk is calculated based on the formula in the Axis section of these settings that takes value of each category within Risk factors that is selected by risk analysis team. Another parameter that influences where the risk will fall within the matrix is Value of each Definition within Scale of Axis that is set up above the matrix in Settings.
  2. Editing names and parameters of Axis, Definitions and its values is described in the article How to set up and edit horizontal and vertical axis of the risk matrix?
  3. To arrange fields (rectangles) in the matrix click on edit button  that appears once cursor is placed on the field

 

  1. In the window that opens change the name or color if necessary (by default it is labeled by letters and numbers of two values that crossed in this field according to Scale section of Axis set up). To confirm click on 

 

  1. As you made changes to the Title and/or color of a certain field, you will see them immediately on the matrix

 

  1. Set up the Risk Matrix according to standards and procedures used in your company for the risk analysis to comply with corporate policies.

Usually “green” field color is used for acceptable risk ratings, “yellow” or “orange” color for medium risk, which requires additional mitigation measures to reduce it to acceptable “green” level and “red” color for unacceptable high risks, which mean that job cannot be performed with this level of risk unless mitigation measures reduce it to “green” level. Risk matrix setup determines which level of Severity and Probability of the risk is “acceptable” by marking these fields as “green” and which level is unacceptable, marking such boxes into “red”, “orange” or “yellow” color.


    • Related Articles

    • How to set up and edit horizontal and vertical axis of the risk matrix?

      How to set up and edit horizontal and vertical axis of the risk matrix? Similar questions:  Where to edit axis used for Initial risk matrix?  In order to change or set up the risk matrix axis user needs relevant rights within his/her Role in the ...
    • How to create or edit a risk factor for initial risk calculation?

      How to create a risk factor for initial risk calculation or edit the existing one? Similar questions:  Where to change risk factors used for Initial risk matrix? In order to change or add a risk factor user needs relevant rights within his/her Role ...
    • How to determine the initial risk?

      How to determine initial risk? Similar questions:  How to calculate initial risk associated with the event? An event that happened or could’ve happened (for near misses) is taken into consideration itself when analysing factors of the risk matrix. ...
    • How to indicate risk components associated with the event ?

      How to indicate associated hazards with the event? Similar questions :  Where to indicate risks associated with the event? Event information can be edited or updated by users that have necessary rights for this within their Role in CONFORMiT ...
    • Creating new Risk from Event details or linking an event to the existing Risk

      Similar questions: How to create a Risk Analysis from the Event details page? How to link an existing Risk Analysis to the Event from Web interface events details page? Creating a new Risk or linking the existing one is possible for tenants that have ...