How to view the Intervention progress in Web interface?

How to view the Intervention progress in Web interface?

Similar questions:  Where to see the time when lockout has started and when ended? How to see in web interface which lockout steps have been performed already?

Intervention progress tool also keeps information about changes made during isolation and comments of the user applying energy controls. This data allows to correct possible errors in the Lockout Procedure.

·       From the home page go to  module.

Find the Intervention that you need to view the progress for (use the filter tool if necessary) in the   or  and click on ID to open details

·      Progression field in the lower right part of the screen shows the Procedure status, date and time when controls have been implemented or when the implementation started (depending on the stage) and list of materials that were applied

  1. Clicking on  will open the progress details

-        name of the user and time span during which steps have been performed:


- check mark  means that controls have been implemented (appears once section of the procedure, such as Isolation or Return to Service is completed)

-      a comment to the step may be viewed by clicking on   in case user that’s performing the lockout has added a comment

-       any deviations from the procedure that were done while performing the lockout: